Continued work on the 13th green drainage

Continued work on the 13th Green - after locating the crushed connector joint half way through the main pipe going through the middle of the green we then cleared the trench ready to be gravelled and new pipe connected up, once the pipe was laid down we gravelled over the top and continued to fill with gravel until it met the line on the original USGA SPEC design, a 3-4 inch binding layer was then put in before 14 inches of rootzone before being levelled and ready to lay the turf back down.